This project consisted of a complete mechanical and electrical renovation design of an existing two-story building.
Hardee’s Restaurants
DAE completed the HVAC, plumbing and electrical design for the remodel of existing Burger Chef restaurants into Hardee’s restaurants. Our initial project with Hardee’s developed into a two-year, repeat-project relationship.
Texas Roadhouse
Anderson
This project consisted of a tear-down of the existing building, and building the new restaurant on the existing site. DAE successfully completed design for a tricky utility connection, and an external grease trap.
Indianapolis
DAE completed mechanical, electrical and plumbing design for construction of this new restaurant.
Heritage Transport Center/MicroNutrients
Design-Aire completed HVAC design for this transportation maintenance facility and a subsequent design of a chemical recycling plant.
DuPont DeNemours & Company
Design-Aire Engineering was responsible for HVAC renovation and detailed cost estimate of this 100% outside air ventilated quality control laboratory.
Wavetek, Inc.
At this industrial facility, design of the HVAC and exhaust was completed for the production plating and Class 1,000 clean room. Due to the depth of the plating tanks, the design required a unique push-pull exhaust technique to contain acid and caustic fumes.
Naval Avionics Center
Mechanical design of a Class 100 clean room, providing an ultra-clean air environment required for photographic processing. This project involved the interface with existing utilities and production schedules while meeting tight budget limitations.
Merico Oil
Design-Aire Engineering has completed several projects at Citizens Gas & Coke. This includes mechanical design for renovation to the dust collection system, hot water heater design, an acoustical study and solution to hopper house sound problem.
Aluminum Finishing Corporation
DAE assisted the owner in obtaining VOC discharge permit through the Environmental Protection Agency for an industrial painting operation. Emissions were reduced, from in excess of 25 tons VOC’s per year to approaching zero, by application of a recuperative thermal oxidizer designed by DAE
Crestwood North
Built in 2002-2003 for Crestwood North Apartments Partnership, this 92,600 square foot three story building accommodates 84 units.